- Application for Demolition
- 12-16-2010
- Hearing to Delay Demolition
Permit - 1-3-2011
- 90 Delay Effective 12-16-2010
- Authenticity Mtg on Site -
1-20-2011
- Grant Transfer Letter Rcvd
in Harwinton - 2-8-2011
- Harwinton House Committee
approved by Harwinton Board of Selectmen 2-15-2011
- Addition to State Register
of Historic Places
2-17-2011 for Nomination and 3-2-2011 for Approval
- Harwinton House Committee
Kick-off Mtg 2-24-2011
- Harwinton Board of Finance
Approval 3-3-2011
- Harwinton Town Mtg 3-15-2011
(Approved 71 - 57)
- DECD Meeting in Hartford 3-22-2011
- Agreement signed with Glastonbury
Restoration 3-24-2011
- Agreement signed with the
Town and the Appelts 3-27-2011
- Pre-Grant Application for
Site Feasibility Study 3-31-2011
- Work commencing at 585 Canoe
Hill Road 3-29-2011
- Storage trailer purchased
and delivered to site 4-7-2011
- Storage Trailer #1 loaded
and arrives in Harwinton 5-9-2011
- Storage Trailer #2 purchased
and delivered to site 5-9-2011
- Hearth Stones delivered to
Harwinton on 5-13-2011
- Storage Trailer #2 loaded
and arrives in Harwinton 5-14-2011
- Work completed in
New Canaan 5-14-2011 - Deadline Met
- Deconstruction documents received
and reviewed 7-14-2011
- A Preferred site has been
selected on Bentley Drive west of the Town Hall. 10-12-2011
- Favorable Soil Report received
10-26-2011
- Semi-Annual Financial Report
filed with D.E.C.D. 1-11-2011
- Historical Society is activly
identifying fund raising ideas needed to raise the
house. (ongoing)
- An RFP has been posted for
a Site plan to be developed.
- The Greater Litchfield Preservation
Trust Inc. has committed to funding the matching portion
of an HPTAG grant. Pre-application for the HPTAG has
been filed and approved.
- A letter of recomendation
for the Architectural firm has been submitted to the
Board of Selectmen for approval.
- Amaya Architects (Using Roy
F. Gilley III AIA as Historical Consultant) has been
selected as the preferred Architectural firm.
- Work is underway to apply
for the HPTAG (Historic Preservation Technical Assistance
Grant) with a deadline of Feb 1, 2013.
- March 15, 2013 letter recieved from the Connecticut Trust that we have been awarded the HPTAG. The combination of this grant and the matching funding provided by the Greater Litchfield Preservation Trust will equal $21,800.
- Received approval from Inland / Wetlands Commission on November 4th, 2013.
- Received approval from Torrington Area Health for Septic System Design on November 13, 2013.
- Received recomendation from the Planning Commission stating that the project promotes the plan of Conservation and development on historic preservation. (November 13, 2013).
- Received approval from the Fire Marshall on December 9, 2013.
- Received approval from the Zoning Commission, after a public hearing on December 9th, 2013.
Rendering by Amaya Architects of Orange CT.
All donations
can be made by mailing a check to:
Town of Harwinton
Harwinton House Restoration
100 Bentley Drive
Harwinton, CT. 06791
For Progress Photo
Gallery 
|